File #: 2018-033    Version: 1 Name:
Type: Action Item/Other Items Status: Passed
File created: 1/2/2018 In control: Board of Directors
On agenda: 1/19/2018 Final action: 1/19/2018
Title: Resolution - Approval of Amendment to 2018 Key Performance Indicators Plan - J Beggs
Attachments: 1. 2016-01-16 Key Performance Indicators
Related files: 2018-049

Title

Resolution - Approval of Amendment to 2018 Key Performance Indicators Plan - J Beggs

Other Info

Submitted By: Julie Beggs

Department: Corporate Services

Financial Impact and Cost/Benefit Considerations:

 

Discussion

The Board of Directors may consider approving the following updates and amendments to the 2017-2018 Key Performance Indicators (KPI) Plan. 

                     SAIDI, ARCOS and Estimated Time of Restoration will be calculated on a rolling 12 month basis, instead of year to date. 

                     ARCOS targets are reduced by 5% each, to 70-75-80%. 

                     The target for Energy Audits are split into a P1/P2 target. 

                     Utilization of volunteer time changes will be removed in alignment with new Volunteer Participation Policy. 

                     The metric for Number of PEC-Sponsored Volunteer Opportunities will be replaced with PEC-Sponsored Volunteer Activities with a target of 1 / 4  - 2 / 5  - 3 / 6 and a category weight of 30%.

 

Body

BE IT RESOLVED BY THE BOARD OF DIRECTORS that the amendments to the 2017 - 2018 Key Performance Indicators Plan as outlined to the Board in the attached Plan amendment, with any modifications made by the Board this day, are hereby approved; and

 

BE IT FURTHER RESOLVED that the Chief Executive Officer, or designee, is authorized to take all such actions necessary to implement the 2017 - 2018 Key Performance Indicators Plan and otherwise effectuate the purposes of this resolution.