Pedernales Electric Cooperative – Board of Directors Meetings

File #: 2022-402    Version: 1 Name:
Type: Action Item/Other Items Status: Passed
File created: 11/15/2022 In control: Board of Directors
On agenda: 12/16/2022 Final action: 12/16/2022
Title: Resolution - Approval of Filing of Application as to its Certificate of Convenience and Necessity (CCN) with Public Utility Commission of Texas for Service Territory Boundary Exception - Llano County - A Hagen/C Powell
Related files: 2022-389

Title

Resolution - Approval of Filing of Application as to its Certificate of Convenience and Necessity (CCN) with Public Utility Commission of Texas for Service Territory Boundary Exception - Llano County - A Hagen/C Powell

 

Other Info

Submitted By: Don Ballard

Department: General Counsel

Financial Impact and Cost/Benefit Considerations: As discussed in Executive Session.

 

Discussion

Pursuant to Chapter 37 of the Texas Utilities Code, the Public Utility Commission of Texas (“PUC”) requires a certificate of convenience and necessity (“CCN”) for an electric cooperative (and other utilities) to serve the public in its service territory. For an electric cooperative to provide service to a consuming facility outside of its territory, an application for a service area exception must be filed with and approved by the PUC. Applications for service are submitted by prospective members and agreed to by the CCN holder where the service will be provided and by the entity that will be providing service.

 

Body

NOW THEREFORE BE IT RESOLVED BY THE BOARD OF DIRECTORS OF THE COOPERATIVE, that the Cooperative file an appropriate application for a service area exception with the Public Utility Commission of Texas as discussed in Executive Session; and

 

BE IT FURTHER RESOLVED, that the Chief Executive Officer or designee is hereby authorized to take such actions as needed to implement this resolution.