File #: 2018-322    Version: 1 Name:
Type: Executive Session - Contract and Competitive Matters Status: Agenda Ready
File created: 8/21/2018 In control: Board of Directors
On agenda: 9/17/2018 Final action: 9/17/2018
Title: Resolution - Approval of Wirtz-Mountain Top T-Line Pole Order - E Dauterive

Title

Resolution - Approval of Wirtz-Mountain Top T-Line Pole Order - E Dauterive

 

Other Info

Submitted By: Brian Gedrich

Department: Engineering

Financial Impact and Cost/Benefit Considerations: As discussed and provided in Executive Session

 

Discussion

Recommendation to approve the purchase of 187 galvanized steel transmission poles necessary for the rebuild and upgrade of the existing Wirtz to Johnson City (T313) and Johnson City to Mountain Top (T317) transmission lines.  This project addresses various issues that have been identified with these lines including NESC clearance violations, structural issues, and failed pole inspections.  The transmission line upgrade improves the existing line by adding the ability to convert the 69 kV transmission voltage to 138 kV, allowing for bundled conductor construction to increase line rating, adding optical ground wire fiber to improve communications and reliability, and allowing an additional transmission line to be installed on the same structures.

 

Body

BE IT RESOLVED BY THE BOARD OF DIRECTORS OF THE COOPERATIVE, that the Cooperative approve the purchase of steel transmission poles for the 2018 CIP Project T313 and T317 Transmission Line Rebuild and Upgrade; and

 

BE IT FURTHER RESOLVED, that the Chief Executive Officer or designee is hereby authorized to take such actions as needed to implement this resolution.