File #: 2025-233    Version: 1 Name:
Type: Action Item/Other Items Status: Passed
File created: 7/14/2025 In control: Board of Directors
On agenda: 8/15/2025 Final action: 8/15/2025
Title: Resolution - Approval of Old Eighty-One Substation Construction Contract - J Greene
Attachments: 1. Construction Contract Old Eighty-One Substation 2025-233 Rev0

Title

Resolution - Approval of Old Eighty-One Substation Construction Contract - J Greene

 

Other Info

Submitted By: Jonathan Greene

Department: Engineering

Financial Impact and Cost/Benefit Considerations: As discussed in Executive Session.

 

Discussion

As part of the 2024 Capital Improvement Plan, approved by the Board in November 2023 (2023-333), Pedernales Electric Cooperative, Inc. (Cooperative) included a project to construct a new substation in the Kyle area. This project provides the ability to serve additional growth in the area, increases contingency to improve reliability, and offloads distribution circuits from Lehigh Substation, Kyle Substation, and Goforth Substation.

 

Body

BE IT RESOLVED BY THE BOARD OF DIRECTORS OF THE COOPERATIVE that the Cooperative is authorized to execute a construction contract to build a new substation in the Kyle area consistent with the discussion in Executive Session; and

 

BE IT FURTHER RESOLVED that the Chief Executive Officer or designee is authorized to take all such actions as needed to implement this resolution.