Legislation Details

File #: 2026-232    Version: 1 Name:
Type: Action Item/Other Items Status: Agenda Ready
File created: 7/7/2026 In control: Board of Directors
On agenda: 8/21/2026 Final action:
Title: Resolution - Approval of Construction Contract - T328 Buda-Manchaca Transmission Line Upgrade - J Greene
Attachments: 1. Construction Contract T328 Buda-Manchaca Final Presentation 2026-232
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Resolution - Approval of Construction Contract - T328 Buda-Manchaca Transmission Line Upgrade - J Greene

 

Other Info

Submitted By: Jonathan Greene

Department: Transmission

Financial Impact and Cost/Benefit Considerations: As discussed in Executive Session and the confidential term sheet.

 

Discussion

As part of the 2025 Capital Improvement Plan, approved by the Board in November 2024 (2024-331), Pedernales Electric Cooperative, Inc. (PEC or Cooperative) included a project to upgrade the T328 Buda-Manchaca transmission line. The line will be rebuilt with steel monopole structures and single Suwannee conductor. 

 

This project will enhance PEC’s system resiliency and increase the capacity of the transmission line.

 

Body

BE IT RESOLVED BY THE BOARD OF DIRECTORS OF THE COOPERATIVE, that the Cooperative is authorized to execute a construction contract to complete the work required for the upgrade of T328 Buda-Manchaca transmission line as described in Executive Session and in the confidential term sheet; and

 

BE IT FURTHER RESOLVED, that the Chief Operations Officer - Transmission, or designee, is authorized to take all such actions as needed to implement this resolution.