File #: 2025-009    Version: 1 Name:
Type: Action Item/Other Items Status: Passed
File created: 12/26/2024 In control: Board of Directors
On agenda: 1/17/2025 Final action: 1/17/2025
Title: Resolution - Approval of Whitestone T1 and T2 Upgrade Construction Contract - J Greene
Attachments: 1. Whitestone Substation T1 and T2 Upgrade Construction Contract 2025-009 Final

Title

Resolution - Approval of Whitestone T1 and T2 Upgrade Construction Contract - J Greene

 

Other Info

Submitted By: Jonathan Greene

Department: Chief Operations Officer - Transmission

Financial Impact and Cost/Benefit Considerations: As discussed in Executive Session.

 

Discussion

As part of the 2024 Capital Improvement Plan, Pedernales Electric Cooperative, Inc. included a project to upgrade the Whitestone Substation to add capacity to serve additional load and maintain reserve capacity.  This project includes upgrading Whitestone transformers T1 and T2 to 46.7 MVA. The distribution side of the Whitestone Substation will be rebuilt, adding one new feeder.

 

Body

BE IT RESOLVED BY THE BOARD OF DIRECTORS OF THE COOPERATIVE, that the Cooperative execute the Whitestone T1 and T2 Substation Construction Contract as described in Executive Session; and

 

BE IT FURTHER RESOLVED, that the Chief Executive Officer or designee is authorized to take all such actions as needed to implement this resolution.