Pedernales Electric Cooperative – Board of Directors Meetings

File #: 2024-169    Version: 1 Name:
Type: Action Item/Other Items Status: Passed
File created: 4/30/2024 In control: Board of Directors
On agenda: 6/21/2024 Final action: 6/21/2024
Title: Resolution - Approval of Yarrington Substation Construction Contract Amendment - E Dauterive
Related files: 2024-152

Title

Resolution - Approval of Yarrington Substation Construction Contract Amendment - E Dauterive

 

Other Info

Submitted By: Eddie Dauterive

Department: Engineering

Financial Impact and Cost/Benefit Considerations: As discussed in Executive Session.

 

Discussion

In October 2023, the Board approved a construction contract for Yarrington Substation. Due to site conditions, additional civil work is required. A change order to cover the additional construction cost is requested.

 

Body

BE IT RESOLVED BY THE BOARD OF DIRECTORS OF THE COOPERATIVE, that the Cooperative approve the change order to complete the additional project scope at Yarrington Substation as described in Executive Session; and

 

BE IT FURTHER RESOLVED, that the Chief Executive Officer or designee is authorized to take all such actions as needed to implement this resolution.