Title: Resolution - Approval to Amend Tariff and Business Rules - C Powell/B Headrick
Attachments: 1. Approval to Amend Tariff and Business Rules Presentation 2026-335, 2. Tariff and Business Rules - Effective Mar 1 2027_Redline 2026-335, 3. Tariff and Business Rules - Effective Mar 1 2027_Clean 2026-335
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Resolution - Approval to Amend Tariff and Business Rules - C Powell/B Headrick

 

Other Info

Submitted By: Audri Nelson/Bridget Headrick

Department: Compliance and Regulatory

Financial Impact and Cost/Benefit Considerations: Expenditure of Cooperative funds is not anticipated to be impacted; expenditure of staff time not anticipated to be impacted.

 

Discussion

Pursuant to Texas Utilities Code Section 41.055, the Board of Directors of Pedernales Electric Cooperative, Inc. (the “Cooperative”) “has exclusive jurisdiction to: (1) set all terms of access, conditions, and rates applicable to services provided by the electric cooperative, . . . , including nondiscriminatory and comparable rates for distribution . . . (7) establish and enforce service quality standards, reliability standards, and consumer safeguards designed to protect retail electric customers . . . . ; and (12) make any other decisions affecting the electric cooperative's method of conducting business that are not inconsistent with the provisions of [Chapter 41 of the Texas Utilities Code.]”

 

The Cooperative has established a Tariff and Business Rules Management Procedure to manage the review of, and amendments to, PEC’s Tariff and Business Rules. The Tariff and Business Rules consists of both the rate structures and rate schedules for Members governed generally by PEC’s Rate Policy and associated rate plans, as well as the business rules and procedures for establishing service, disconnecting of service, and other operations of the Cooperative.

 

The Cooperative officially adopted the Tariff in 2009 and then consolidated the Tariff with the Business Rules in December 2016 (collectively, the “Tariff and Business Rules”). Numerous modifications and amendments have been adopted to various sections of the Tariff and Business Rules over the years. Most recently a restructure of the Tariff and Business Rules was approved in February 2020.

 

Since that period, certain business processes and practices have been updated. As a result, the following changes to the Tariff and Business Rules, among others, are proposed. These changes include both substantive and non-substantive changes. The Tariff and Business Rules is organized into the following components:

 

Section 100: Definitions

Section 200: Description of the Cooperative’s Service Area

Section 300: General Service Rules and Regulations

Section 400: Facilities Extension Policy

Section 500: Rates

Section 600: Distributed Generation Interconnection Policy

 

The Cooperative asks the Board to consider these amendments which aim to address business and policy issues and conform to the Member’s interaction with the Cooperative.

 

 

 

All/ General

 

• Changed Delivery Charge term to Distribution Charge

Section 100

Definitions

• Updated Capacity Demand clarifying the adjustment for power factor and establishing a minimum of the highest value in the preceding 11 billing periods. • Defined Distribution Energy as the amount of energy measured as the greater of kWh delivered or received within the billing period, as applicable. • Updated Encroachment to remove obstructions and obstacles and align with the Easement Encroachment Review Application. • Updated Landlord Account Provision and added Landlord protections from additional establishment fees after Tenant’s disconnection. • Updated Peak Demand clarifying the adjustment for power factor and establishing a minimum of the highest value in the preceding 11 billing periods, and 50kW.

Section 200

Description of the Cooperative’s Service Area

• No changes proposed

Section 300

General Service Rules and Regulations

• Changed process for Landlord when Tenant is disconnected with notice, service at the unit will not automatically be re-established without Landlord authorization. • Added Permanent Disconnection section under Voluntary Member Disconnection clarifying that a Member can request either Permanent or Temporary Disconnection. • Removed meter exchange fee section related to Advanced Metering Opt-Out Program to clarify the Cooperative will no longer allow Member opt-out and adjusted meter reading provisions to relax monthly requirement and allow estimates.    • Added language clarifying owner’s responsibility and acceptable back billing for improper meter identification that is re-labelled, altered, removed, relocated, or changed within a Multi-Family Dwelling without Cooperative approval. • Added language clarifying Member requests related to Easement Review (Basic) vs. Easement Release Review (Advanced). • Clarified Easement Encroachment Review and increased the fee. • Added section for filing or recording fees.

Section 400

Facilities Extension Policy

• Added term ‘application fees’ to list of fees or charges the Cooperative can require to be paid for each facility extension.

Section 500

Rates

• Changed Delivery Charge to Distribution Charge and clarified meaning as delivered or received (highest volume of flow in or out) within the billing period.  • Added definition language to the Base Power Charge to include realized and unrealized hedging costs and settlements. • Reduced Base Power Rate. • Adjusted Time of Use (TOU) table and time periods. • Eliminated Sustainable Power Credit Section. • Interconnect TOU credits in excess or unused will carry over month to month up to 12 months - 12 month rolling expiration of first in first out basis. • Increased Distribution Charge rate. • Simplified Advanced Metering Opt-Out fees. • Removed Sections: Residential, Farm and Ranch Service, Interconnect Rate; and Residential, Farm and Ranch Service, Interconnect Rate, with renewable energy rider. • Implemented a Large Power and Industrial Power capacity demand ratchet that will apply an 80% minimum on an 11-month look-back period. • Included language in Large Power section to clarify non-residential interconnect rate class. • Modified definitions of Peak Capacity Charge and Capacity Demand Charge for both Large Power and Industrial Power. Fee Schedule Revisions • Increase Open Records and Subpoena Response Service Fess to $80.00. • Changed Advanced Metering Opt-Out Program - Meter Reading and Processing Fee to $40.00 monthly processing fee per meter. • Added Meter Verification Fee - $500.00 per occurrence, same as Meter Tampering Fee. • Clarified Easement Review Fees - Basic, Advanced, Encroachment, Amendment. • Added Easement Release Review Fee (Advanced) - $400.00 or actual cost, whichever is greater. • Increased Easement Encroachment Review Fee from $775.00 to $825.00 or actual cost, whichever is greater. • Added Filing/Recording Fee - At cost.

Section 600

Distributed Generation Interconnection Policy

• Added language to exclude opt-out meters from Distributed Generation (DG) interconnection. • Added language for Cooperative standards related to safe and reliable operation, in conjunction with regulatory standards. • Clarified language regarding submission of new interconnection applications if expanding an existing DG system. • Added language for acceptable trip fee charge and disconnection with or without notice if DG facilities are operating without permission to operate.  • Added ‘in aggregate’ language to cover all applications associated with a DG interconnection. • Added terms and conditions language to Cooperative’s review of proposed DG systems.

 

Body

BE IT RESOLVED BY THE BOARD OF DIRECTORS OF THE COOPERATIVE that the amendments to the Tariff and Business Rules as attached and presented this day is approved with such changes, if any, as were discussed and approved by the Board; and

 

BE IT FURTHER RESOLVED that these changes are to become effective March 1, 2027; and

 

BE IT FURTHER RESOLVED that the General Counsel, or designee, are authorized to take all such actions as needed to implement this resolution.